November 2021

50035 Ark Royal departs Bewdley South working a goods train training working on 23rd Octob
50035 Ark Royal departs Bewdley South with a training goods train working on 23rd October 2021. Credit Tony Carwithen

Welcome to your latest edition of Express Points!

Welcome to your November Express Points. The main season trains are finished but public trains start again next week with Steam in Lights, and we've information on how you can enjoy the SiL magic on the test trains. This is just the beginning of our hugely important Christmas services, where volunteer help is still sought please.

We’ve also highlights of the planned winter works and events for next year. A big part of 2022 will be at Bridgnorth's loco works where, subject to our stakeholders’ further financial support, we’ve the opportunity to make the roof project into a roof and crane one. Helen Smith is also looking for your input on the Railway’s evolving strategy, and there’s an appeal from Chris Bond to support the critical work of the PWay team.

With Christmas in mind, Michael Dunn has some ideas for your lists, presents and stockings! The long evenings are here again, and to help you through we’ve a couple more films from our YouTube channel.

There are also updates on our application to the Cultural Recovery Fund and for our shareholders on travel benefits. Throw in news on our locomotives, coaches and other stories from around the Railway and we’ve another bumper issue for you!

 

Lesley and Patrick, co-editors

The Express Points team is Lesley Carr, Patrick Hearn, Amy Baker and Nicola Fox

Next edition Thursday 9th December

It’s all go as the SVR steps into Christmas

Hampton Loade Steam in Lights 2020. Sam Lench.jpg
Sunflower Saxes at the SVR 1 (Copy).jpg

It’s less than a week before the Railway’s seasonal services start with an ambitious programme, very healthy ticket sales, lots of activity underway – and lots still to do!

 

The spectacular Steam in Lights service from Bridgnorth starts on 19th November and runs on selected dates until 23rd December.

 

“This received excellent reviews in previous years,” said head of visitor experience Michael Dunn. “And in 2021 it’s going to be even better, with a superb, professional pre-departure show and twice the number of lineside displays. We've already sold as many tickets this year as we did in total in 2020, which is fantastic. Having extra services this year means we still have seats available and we’ll continue to push this to a sell-out.”

  

A huge amount of work goes into this event, and more volunteer help is needed (see separate article) both at Bridgnorth Station, where teams welcome guests on 22 nights of services, and to decorate the carriage set, both inside and out.

Enchanted Express services run from Bridgnorth on selected dates from 27th November. This new event has proved very popular, and is now almost fully booked! A few extra compartments have been made available because of high demand.  

  

It will also be a pleasure to welcome guests back to the Carol Trains, operating from Kidderminster every Friday and Saturday from November 27th to December 18th. This year, visitors will enjoy a festive concert at The Engine House with performances by local choirs, bands, groups and orchestras. A shout out to the Highley station and Engine House teams! 

 

Sales for our flagship (or should that be headboard?) Santa Trains on dates between 27th November and 24th December are going very well, with many trains sold out. There’s better availability on the first weekend (27th and 28th November) and 20th to 22nd December. 

Much work has already been undertaken, and the presents are wrapped, unloaded and stored away thanks to the ‘present gang’ on 5th November. A lot of activity has also taken place at Kidderminster and Arley stations, and by the Santa team. Again, further volunteer help is required (see separate article.) 

“The events team has put together a tremendous package of Christmas events,” said managing director Helen Smith. “The last two years have been so hard for all of us, so it’s a real joy to welcome visitors returning to the Railway, and to celebrate the season with them. The success of the programme is essential as we secure our future, repay our CBILS loan and continue our recovery. Everyone, both volunteers and paid staff, is putting in a truly tremendous effort behind the scenes. Thank you so much!” 

Photos: Hampton Loade decorated for Stem in Lights 2020. Sam Lench

Below: The Sunflower Saxes at the SVR

It’s all go as the SVR steps into Christmas

SVR (Holdings) shareholder benefits

We reported in October’s Express Points that at the SVR (Holdings) Plc (SVRH) annual general meeting the then chairman Nick Paul had put a moratorium on the decision to make changes to shareholder benefits, until the board had the opportunity to reflect and review the decisions.


Since then, the SVRH board has discussed further and agreed the proposed increases for 2022 should go ahead. However, in response to the concerns raised, it also agreed that no further changes will be considered until after the shareholders’ focus group (see below) has reported back to them. The levels proposed for implementation in 2023 will not be brought in.


As promised, incoming SVRH chairman Mike Ball wrote on 6th November to all shareholders. There are different versions, depending on the level of shares held, which confirm the reasoning for the decisions and full details of the changes as they affect each shareholder.

1501 leaves Bewdley between the houses on 29th October. Photo Bob Green.jpg

Mike reiterated the SVR is indebted to its shareholders, members and donors and is extremely grateful for their support. He also asked shareholders to remember both the difficult financial situation, and that SVRH is a not-for-profit company with any surplus ploughed back into the Railway.


A reminder that the board is looking to recruit several shareholders to help conduct a full review of the shareholder benefits system before the next AGM in June 2022. If you would like to help, please contact victoria.evans@svrlive.com by 15th November, including your full name, shareholder numbers and the reasons why you would like to be included in the group.

Photo: 1501 leaves Bewdley between the houses on 29th October. Bob Green

SVR (Holdings) shareholder benefits

The SVR applies to the Culture Recovery Fund for Heritage – round 3 ‘continuity support’

40106 on 30th October 2021with wreath and tribute to local enthusiast and regular SVR visi

The Railway recently submitted a bid for almost £600,000 to the third round of the Culture Recovery Fund for Heritage. This new ‘continuity support’ funding was announced in June and is aimed at helping heritage organisations as audiences begin to return, thus ensuring a vibrant future for the culture sector as the nation recovers from the pandemic. 

In November 2020, the SVR received a grant of £906,000 from Round 1 of the Department for Digital, Culture, Media and Sport’s package of support to protect the UK’s culture and heritage sectors from the economic impacts of Covid-19. This helped the Railway survive the initial impacts of lockdown.

The round 1 grant helped to fund staff salaries from 1st October 2020 to 31st March 2021 together with additional CCTV and security systems to protect the Railway and its rolling stock, the recruitment of a health & safety manager, and the development of the SVR’s digital marketing and communications. 

This helped the Railway to reopen and begin to operate again after the initial lockdown but, like most other heritage organisations across the UK, the very significant reduction in visitor numbers, which resulted from further lockdowns and social distancing restrictions, had a devastating impact on the organisations’ finances.

Severn Valley Railway (Holdings) plc has consequently submitted an application to this third round of the Culture Recovery Fund in liaison with the SVR Charitable Trust. This has been a major undertaking, requiring the submission of detailed financial accounts, cash flows and a Business Actions plan which has required significant work by a number of key people.

The maximum amount that we could apply for under this round of funding was just under £600,000 and we should receive notification of the outcome by mid-December. 

Photo: 40106 Atlantic Conveyor on 30th October 2021 with wreath and tribute to local enthusiast, supporter of the SVR and Diesel Traction Group, and regular visitor Gerald 'Ged/Jed' Hapel, who passed recently. Jason Hood

The SVR applies to The Culture Recovery Fund

We’re very nearly Home & Dry!

The team in charge of delivering the Home & Dry project at Bridgnorth’s locomotive works has discovered a suitable second-hand crane that will provide the final pieces in the jigsaw of this essential work. The race is now on to secure the final tranche of funding to secure the purchase of the crane.

In October’s issue we reported that phases 1 and 2 of the Bridgnorth locomotive works project are funded and in project delivery - the roof, electricals, cladding, ground works and civils works.

Last week, volunteer project manager Antony Bartlam and head of engineering Martin White made an inspection visit to the Northampton site where the crane is currently being stored, along with its steel support structure.

“This was a real find for the project,” said Antony. “This second-hand 6.3 ton capacity crane is exactly what we need, and means that we won’t have to order and pay for new steelwork.

Home and Dry Crane.png

“The issue, however, is we don’t yet have sufficient funds to order and secure the crane and supporting steel structure. This means potentially we could lose it. To purchase a new crane and steelwork would mean an associated increase in costs.”

The Trust confirmed that so far £430,000 has been raised; that’s more than 90% of the £475,000 total needed to ensure that all aspects of the works can go ahead. The Charitable Trust’s executive director Shelagh Paterson explained, “With just £45,000 left to raise, we are tantalisingly close to achieving the target. We are so grateful for the amazing support shown for this project and hope one final push should see the goal achieved”.

“This project is being led and assisted by volunteers,” added Antony. “And this means we’re saving more than £40,000 on fees and labour costs. This really is a once-in-a-generation chance to transform the workshops into a great working environment for the future.”

The SVR’s film team is creating an updated video about the project, which includes footage of the visit that Antony and Martin made to inspect the crane. This will soon be released on the SVR’s YouTube channel.

To donate, please visit www.svrtrust.org.uk/home-and-dry. Or if you’ve already donated but could spare a few extra pounds to help the project to achieve its goal, please make a small donation on the project’s JustGiving page at www.justgiving.com/home-and-dry

Photo: inspecting cranes in Northampton! Lesley Carr

We’re very nearly Home & Dry!

Get Christmas wrapped up with the Severn Valley Railway 

Image.jpeg
Image (1).jpeg

There’s no better place to shop than www.svrshop.co.uk for everybody who loves the Railway, as head of visitor experience Michael Dunn told Express Points. 

 

Our shops have plenty of Christmas gifts to choose from, with our Severn Valley Railway merchandise - including our popular Christmas jumper. Our exclusive 2021 SVR baubles are back too, but be quick as once they’re gone they’re gone! 

 

Other new Christmas lines include both physical and digital gift vouchers, both of which you can customise and can be bought now for any future travel in 2022, including special events! 

If you spend £75 or more online you also get a free calendar for 2022, simply add the calendar of your choice to your basket and enter the code SVRCALENDAR at checkout. 

Across the shop, we are adding more products daily. Head to www.svrshop.co.uk now to explore the full range. All items are also available in our shops, which will be open in line with Christmas services.

Get Christmas wrapped up with the SVR

Lest we forget…

On Sunday 14th November, Kidderminster Town Station will be holding its yearly remembrance service, and you are warmly invited to attend. 

The service will begin at 10:45pm, there will be a ceremony of hymns and prayers on the concourse. The service will pause for the customary two-minute silence at 11:00am.

Photo: 43106 runs past field of poppies at the new nature reserve at Dropping Well Farm, between Kidderminster and Bewdley on 21st June 2021. John Sherratt

43106 runs past field of poppies at the new nature reserve at Dropping Well Farm, between
Lest we forget…

Remembering our wartime connections

8f&Gordon_LM.JPG

In this week of remembrance, the Railway is commemorating the anniversary of the dedication of 48773, owned by the Stanier 8F Locomotive Society. Thirty-five years ago, the 8F was officially dedicated as the Memorial Locomotive for the Royal Engineers Railway Sappers who lost their lives in World War Two.

On 27 September 1986, the Very Reverend Peter Haynes, Dean of Hereford, performed the service at Highley, which was attended by senior Royal Engineers officers, representatives of the SVR and the 8F Society. A Roll of Honour commemorating the names of more than 400 Railway Sappers is displayed alongside the locomotive in the Engine House at Highley, where the locomotive is currently on exhibition.

Since its dedication, 48773 has provided a focus for many Remembrance Sunday services held by the SVR.

This year the 8F Society is again providing support for the event, to be held at Kidderminster station under the auspices of station master Geoff Smith. As on previous occasions, 8F Society officers will participate in the reading of names from the Roll of Honour.

Among those names are a number of railway sappers who perished in Britain’s worst maritime disaster of the last century. Two weeks after Operation Dynamo evacuated Dunkirk, there were still elements of the British Expeditionary Force fighting south of the Somme. They were spread across various depots, stores and camps throughout France, many sappers amongst them.

As part of Operation Aerial, HMT Lancastria was sent on a rescue mission to St Nazaire, arriving on 17 June 1940. Tragically, the Lancastria was attacked by the Luftwaffe in the afternoon and sank with the loss of thousands of lives. More than 100 railway sappers perished that day; recorded on the Roll of Honour, a number of these casualties will have their names read out on 14th November at the Kidderminster service.

48773 provides a unique and important link between the Severn Valley Railway and the Corps of Royal Engineers; and the SVR and the 8F Society are proud that the locomotive can play a part in the poignant commemoration of the fallen.

The full list of names on the Roll of Honour can be accessed through The 8F Society website: http://www.8fsociety.co.uk/page34.html 

Remembering our wartime connections

A spooktacular success!

After a sell-out in 2020, extra trains were added to the Halloween schedule this year, with additional 5.30pm departures from Kidderminster. Passengers journeyed to the land of the living dead (or Arley, as it is more commonly known!) where a wide array of spooky characters awaited to strike fear into the heart of the intrepid travellers.  

 

Demand for the event was high once again and both the child-friendly Ghost and adult-oriented Scream Trains sold out.  

 

Feedback from passengers enjoying the event was excellent, describing the experience as “phenomenal”, “brilliant” and “amazing”. Trip Advisor reviews from both new and returning visitors alike sang the praises of all involved. One visitor enjoyed it so much, that he returned the following night… to volunteer! Passenger-turned-volunteer Scott Leese said:

“Me and my family went along and we had so much fun. The following night I went along as a volunteer and joined in helping with the scream scares and acts at the station; it was the most fun I’ve had in years. I can’t wait to do something like this again.” 

 

“The displays at Kidderminster, Bewdley and Arley were bigger than ever,” said events manager Lewis Maddox. ”Our scare teams at each site did a fantastic job at spooking our passengers. A big thank you to everyone who made the event happen, your efforts are appreciated. Bring on next year!” 

Click on the gallery for full screen images, descriptions and credits.

A spooktacular success!

A young engineer of distinction!

Alan Brookes COPY.jpg

Congratulations go to Alan Brookes who, after graduating from the SVR’s pioneering Heritage Apprenticeship Scheme, has just passed his BTEC level 4 engineering qualification with a distinction.

Alan was trained under the Heritage Apprenticeship Scheme, funded by the SVR Charitable Trust thanks principally to supporter donations and grants obtained by the Trust.

 

Within the four-year scheme, a number of young people work and learn by rotating through the different departments; locomotive running, boiler shop, carriage mechanical, and carriage bodywork.

As well as intensive on-the-job training, apprentices work towards nationally-recognised NVQ 2 and 3 level qualifications.

Alan, who is employed as an improver fitter machinist, will continue his studies in engineering management until February 2022. He commented, “Many thanks to everyone at the SVR for the support and opportunities I have received to date to further my knowledge and understanding.”

Shelagh Paterson, executive director for the Charitable Trust added, “This is a huge achievement and it is reassuring to know that we have a growing, qualified, experienced and dedicated younger workforce for our succession planning, as this is key to the future sustainability of the SVR.”

It costs £21,000 to fund an apprentice for one year, and the Railway relies on the generosity of the Charitable Trust's supporters to help pay for this essential aspect of its operation. To help develop and support the SVR's future heritage engineers, please donate at www.justgiving.com/apprentice-scheme 

A young engineer of distinction!

Better communication with SVR’s supporters and visitors

As the pandemic hit us in March 2020 and the first lockdown began, it became apparent how difficult it was to communicate effectively with the SVR’s key stakeholders, including shareholders, members, donors and visitors.

 

The three SVR organisations (SVRH, SVRG and the SVRCT) have separate database systems, none of which ‘talk’ to each other. For example, changes of family circumstances or addresses need to be reported to three different organisations, and the situation is confusing for stakeholders and staff.

Furthermore, it can lead to overlap and waste, where supporters get multiple mailings, or paper mailings when we have an email address on another system.

 

The Railway’s also keen to ensure it correctly offers benefits where appropriate, such as member discounts where people are both members and shareholders.

75069 at Bewdley tunnel with driver Dave Cullinen's last turn on 29th October 2021. Photo

“We do collect some information from our visitors,” said head of visitor experience Michael Dunn. “However it could be much more comprehensive. Technology is changing the way we buy things; you might remember the process you had to go through to book a holiday abroad, now you can do it with a few clicks of your smart phone! And, if you have a supermarket loyalty card, it’s used to gain vital insights into your shopping choices and behaviour.

“Whilst we are not on the scale of the supermarket giants, we have more than 13,000 shareholders, almost 11,000 members and 15,000 donors and we should be communicating with them more regularly. Then, there are up to 250,000 annual visitors to the Railway. If we can better understand their motivations and interests, and how and when they visit, we can convert them into members and donors, helping to put money directly back into heritage.”

Michael added: “For these reasons, we are introducing a new, comprehensive customer relationship management (CRM) system. The three SVR organisations will be able to update information, analyse buying behaviour, offer incentives to book, donate or join, email more regularly and personalise the experience. It will be hard work to set it up but once we are there, it will make a huge difference and enable us to be more efficient and effective, lightening the workload on our teams.”

The introduction of the new CRM system will begin in the first months of next year. Supporters can also be reassured that it meets data protection regulations that ensure data is not misused. Training on the system will be essential for anyone who works in a booking office or an administration role across the Railway. Watch this space for more news!

Photo: 75069 at Bewdley tunnel with driver Dave Cullinen's last turn on 29th October 2021. Photo Bob Green

Communication with supporters and visitors

Christmas event set up

There’s lots to set up for the Railway’s important Santa and Steam in Lights events, and volunteer assistance is needed.  

  

Carriage decoration and rope lights, 11th and 12th November 

The Steam in Lights set will be decorated inside and out. Help is needed in Kidderminster carriage shed (under cover for protection from the elements.) 

  

Steam in Lights at Bridgnorth, 22 dates in November and December  

Volunteers are needed to greet and direct passengers each evening, supervise boarding and alighting, check wristbands, and keep everyone safe on the platform.  

 

Carriage decoration, 15th and 16th November 

All three sets of carriages for Santa will be decorated to look wonderful for passengers. Can you help at Kidderminster Town station to hang up bunting, distribute tinsel and display baubles?

Santa Trains, 27th and 28th November and 4th, 5th, 11th, 12th and 18th to 24th December 

Fancy a day on the train and distributing presents into compartments? Present distributors are needed for every day of operation. Whilst passengers enjoyed the show at Arley, the train will steam to Highley for you to put each child’s present into their family’s compartment.  

  

If you’re able to get involved in any of the above, please email lewis.maddox@svrlive.com or call 01562 757910 (extension 560 on the internal network.) Your help will be very much appreciated! 

Christmas event set up

Fire marshal training - open to all

The next wave of fire marshal training will take place on Friday 19th November at the Valley Suite, Kidderminster.

 

As we go to press, there are vacancies on the afternoon course from 1.30 – 4.00, which is open to ALL staff and volunteers.

This is a great opportunity to develop your skills and knowledge around fire prevention and action to take in a fire.

If you would like to reserve a space, please respond to richard.morris@svrlive.com or zoe.cox@svrlive.com.

Fire marshal training image.jfif
Fire marshal training - open to all

Coming to a TV screen near you this month!

Philip Chatfield chiselling coping stones for Falling Sands Viaduct. Graham Phillips.jpg
43106 Matt Fielding.jpeg

Flint TV visited the Severn Valley earlier this year on two occasions to film different aspects of the Railway for broadcast on Britain’s Scenic Railways, which is shown on Wednesdays at 9pm on More4.  

 

On one visit, the crew spent time with stonemason Philip Chatfield, and on the next, filmed from the footplate of 43106 with driver Bob Drew and fireman Tom Clarke.

The first episode of the series aired on Wednesday November 3rd, but the episode to watch for SVR supporters will be on the 24th November; saving the best until last!  

The SVR is proud to be a part of this programme, which will showcase the skills and dedication the Railway is renowned for. Enthusiasts and members of the public alike will be able to enjoy seeing the SVR in action, in this fantastic opportunity to peek behind the scenes.

Tune in to More4 on November 24th at 9pm to see your favourite heritage railway in operation, looking splendid and doing what it does best!

Photos:

Top, Philip Chatfield chiselling coping stones for Falling Sands Viaduct. Graham Phillips

Below: 43106 catches a glint of sun at Bewdley Tunnel on 17th October. Matt Fielding

Coming to a TV screen near you this month!

Job opportunities

There’s a vacancy for a full time office manager at Bridgnorth ESMP and details are available at https://www.hiredonline.co.uk/employer/9159864/severn-valley-railway-holdings-plc/  

  

In addition, the SVR is continuing to invite applications for several casual contract catering assistants in a variety of locations.

Job opportunities

Stanier Mogul Fund at 50+1!

Amidst the turmoil of the Covid-19 pandemic, 2020 saw the Stanier Mogul Fund (SMF) reach 50 years as a preservation group. The Fund has at last been able to mark the event, as Peter Hudson tells Express Points: 

  

While practical efforts to mark this last year with a special train were thwarted, the Fund finally celebrated by organising an 'SMF 50 Golden Jubilee' charter train on Saturday 30th October 2021. 

  

With a specially-made aluminium headboard, the 9.35 am from Kidderminster to Bridgnorth comprised a set of six GWR coaches, hauled by Ivatt Mogul 43106. A two-hour layover at Bridgnorth enabled the SMF members, family and friends to view the progress of the major overhaul of their locomotive in the works, which will see it return to steam in its original 1934 ‘as built’ guise, with the number 13268 (it was subsequently renumbered 2968, then by British Railways as 42968.) 

The charter then formed a timetabled 12.45 pm for Highley. After a further two-hour visit there, it was the 3.20 pm departure back to Kidderminster. 

  

Peter’s photos show this special arriving at Highley, where the nameplate was removed to take to The Engine House for a large passenger group photo outside. Click on the gallery for full screen images, descriptions and credits.

The SMF issue regular progress reports on the overhaul of 13268 on their website at https://www.staniermogulfund.org.uk/news/

Stanier Mogul Fund at 50+1!

'Foodie' changes in store at the SVR

Following a review of rolling stock, arrangements are being made to allow the return of both on-train dining and buffets next year. It’s hoped that the buffet cars will be in service from April, and that, all being well, on-train dining will relaunch in May.

In addition, the recently appointed executive head chef Lucy Kelly is working with the catering team to explore other dining experiences across the Railway, to find ways of using what’s already in place to expand what the SVR can offer to visitors.

Lucy has worked at award-winning restaurants, catered for celebrities and large-scale, high-profile events. She told Express Points, “I am thoroughly excited about being a part of the culinary team at the Railway, and I want to use my experience and skills to take the food offering at the SVR to a fantastic level of quality. When we bring back our on-train dining experiences next year, these will have a creative and modern twist.”

Another key member of the catering staff is Sophie Poutney, who recently joined the Railway as food and beverage operations manager. She has a wealth of heritage and commercial catering experience, and has worked at the Black Country Living Museum, Alton Towers and Sealife Brighton.

With Christmas fast approaching, Lucy has kindly shared a favourite recipe with Express Points readers – smoked cheddar custard and bacon jam is her twist on traditional cheese and biscuits, which she guarantees will change your Christmas dining experience for the better!

Above: Executive head chef Lucy Kelly at work. Below: Sophie Poultney

Executive head chef Lucy Kelly at work.png
Sophie Poultney.jpg
'Foodie' changes in store at the SVR

Experience the Steam in Lights magic on us!

Paid and volunteer staff are invited to experience the magic and travel on the test trains next Thursday, 18th November. 

Tickets are available on a first come, first served basis. Staff can reserve a maximum of one compartment free of charge and bring along up to five guests (fellow staff, friends or family). A maximum of six people can travel in the compartment. 

 

To book, you’ll need to use the weblink provided in the recent NBI, and follow the instructions, before finally adding your ‘Working Member Unique Identification Number’, preceded by VOL, when prompted.

Trains will depart Bridgnorth at 5.30pm and 7.30pm and you will need to bring your working member or staff pass to check in at the booking office before boarding the train. Please allow time to check in.  

Please note the pre-departure show will not take place on the test train evening, and the refreshment room will not be open. 

Experience the Steam in Lights magic on us!

No time to rest on laurels at Bridgnorth MPD

The Railway may appear quiet on the outside, but behind the scenes efforts are ramping up to prepare for the winter season as Bridgnorth shed master Martin White reports: 

 

Public operations on the Railway are currently stood down, after the end of the main season and the commencement of Steam in Lights. There’s a very brief period in which the MPD can catch up on urgent repairs.

BR standard class 4, 75069, is the Steam in Lights (SiL) loco this year and is currently having a boiler washout to enable it to run for the full cycle of steamings. By the time the last of the Bridgnorth based SiL and Enchanted Express trains have run, the 75’ will have completed close to 30 steamings, the top end of our normal washout cycle (although SVR procedures do allow a few extra days to be worked with prior approval.) 

In the works, 2857 is part way through a number of repairs identified as part of its accumulated mileage-driven valve & piston exam; this work won’t be completed before the Santa services commence. Also in the workshops, 813 has been re-tubed and tested and will hopefully be able to go away on hire very soon, to assist another railway with their Christmas period operations.  

The boiler from 4930 ‘Hagley Hall’ is in the boiler shop having lagging and cladding installed ahead its final fitting in the loco frames. Over in Tyseley, 7812, ‘Erlestoke Manor’, has had a successful out-of-frames boiler steam test, following overhaul by Tyseley Loco Works and EMF volunteers. 

For the SVR’s own loco works, the planning and preparation is gathering pace for the roof and crane project. The contracts for the re-cladding and electrical work have been awarded and the cladding sheets will be ordered by the contractor within the next few weeks, for delivery in May 2022. 

7812 Erlestoke Manor's boiler successfully passes its out of frames steam test 19.10.21. C
Guest Brenda Rainbow and Erlestoke Manor Fund members as 7812 Erlestoke Manor's boiler suc

A small team of representatives from the ESMP paid staff have been considering the future layout of the works, such as the positioning of welding bays and machine tools; any necessary electrical supply and ducting can then be incorporated in the overall plans. In addition to volunteers doing behind-the-scenes planning and administration, others have been completing some pre-requisite infrastructure work on the concrete steps to the main MPD yard pit. Incidentally, some of those volunteers were involved in the original construction of the shed, more than 45 years ago!

These few paragraphs barely do justice to the range of work that is currently taking place on this project, but they do demonstrate that this scheme is for real. It is going to happen! We can all be hopeful that this will be the last winter during which paid and volunteer teams in the shed have to dodge the rain inside! The SVR Charitable Trust has done a terrific fund raising job thus far, but a bit more is still required to enable us to finish the job. So, if you haven’t already done so, please do consider making a donation to the Home and Dry appeal at https://www.svrtrust.org.uk/home-and-dry 

Photos: 

7812 Erlestoke Manor's boiler successfully passed its out of frames steam test at Tyseley on 19th October. Credit Erlestoke Manor Fund

Guest Brenda Rainbow and Erlestoke Manor Fund members. Credit EMF

No time to rest on laurels at Bridgnorth MPD

Your opportunity to shape the SVR’s future strategy

Managing director Helen Smith will shortly announce a series of meetings to progress work on the new SVR strategy. These will take place between now and early 2022. The strategy is centered on three areas; safety, people and heritage. Helen explained more:

“I would like to bring everyone together to focus on shaping the future of the Railway and building on the strong foundations formed over the past 50 years. Please don’t worry; the strategy will not see any radical changes. It’s designed to unite the team, allowing everyone to have their say and contribute to the vision for the future. We all want the SVR to be the best heritage railway to visit, volunteer and work at in the UK. We can only achieve that by actively listening to each other, agreeing a way forward and then working together.”

Helen will host the workshops, along with other members of the senior leadership team. The aim is to encourage staff based at every location to meet and discuss what each of the main strategy headlines mean to them. Helen continued:

Father and son at Kidderminster with 40106 Atlantic Conveyor on 23rd October 2021. Mike An

“During the session we will be exploring what you think we are good at, what needs improvement and any new ideas you would like to see implemented. The workshops will be informal; they’ll start with a short presentation from me about the strategy, then you’ll be chatting through everything in small groups, and reporting back your findings. All ideas are welcome, and I encourage you to come along and join in!” 

Photo: Nigel and Geoff Smith, son and father, at Kidderminster with 40106 Atlantic Conveyor on 23rd October 2021. Mike Anderson

Your opportunity to shape the SVR’s future strategy

Falling Sands reawakening

National Lottery Heritage Fund logo.jpg

Work has restarted on the ‘activity' elements of the Falling Sands Viaduct interpretation project. A combination of Covid-19 and staff changes meant this was put on hold following the successful completion of the restoration work in December 2020. The SVR Charitable Trust’s project delivery manager Hamish Wood tells Express Points more: 

 

The National Heritage Lottery Funded project will see the completion of two exhibition areas, which will introduce visitors to the story of the Severn Valley Railway in the Victorian era, and the people who built it.

 

Researchers are busy tracking down material to illustrate the story and are working with archives and collections around the country. So far, some fascinating material has been collected including early photographs of viaduct construction and the working life of the navvies building them.

 

Some Severn Valley material has been unearthed, and this includes a handbill for the celebratory ‘Opening Ball’ in 1862 and some early GWR tickets for trips on the SVR line, from the collections held at Didcot. 

During the restoration work, the remains of a navvy’s shovel were unearthed from the infill on Falling Sands Viaduct (see Express Points, March 2020.)

 

What appeared to be a mundane find has turned out to be a unique artefact, as there is no known example in existence! The shovel has now been conserved by an SVR volunteer who is a National Trust conservator and will be displayed as part of the new exhibitions at The Engine House. 

Kidderminster College students are developing games for the project, and we plan to incorporate these into the new exhibitions as downloadable interactives. Their work so far is exceptional, and it’s wonderful to be involving this younger audience in the SVR.

As a condition of the National Lottery funding, it’s important that the Falling Sands project engages with the local community. With Covid-19 restrictions lifting, we’re once again actively working with new audiences to encourage their future involvement with our Railway. 

 

For further information on the project please contact Hamish Wood at the Charitable Trust.

Click on the gallery for full screen images, descriptions and credits.

Falling Sands reawakening 

National recognition for the Falling Sands project

The SVR Charitable Trust has announced that the Falling Sands Viaduct restoration project has been shortlisted for a National Railway Heritage Award.

 

The comprehensive project successfully restored the viaduct both operationally and visually, with missing corbelling courses and end piers reinstated.  

 

The restoration of the seven-arched viaduct has been commended by judges for demonstrating “both ingenuity and the value of positive team working with client, professional, contractors and volunteers all contributing to a very successful outcome.” 

 

The Charitable Trust has thanked volunteer Nick Yarwood for his invaluable contribution to the project. Nick attended site daily during the restoration and subsequently drafted the submission to the National Railway Heritage Awards on behalf of the Railway.  

The winners will be announced next month. 

Nick Yarwood at Falling Sands Viaduct. Steve Leath, Express and Star copy.jpg

Nick Yarwood at Falling Sands Viaduct. Steve Leath, Express and Star

National recognition for the Falling Sands project

Resurrecting a lost locomotive class at Bridgnorth

For more than 18 years, volunteers from the SVR-based 82045 Steam Locomotive Trust have been working hard to fulfill a dream. They’re creating a new-build version of a BR Standard Class 3 tank steam locomotive, and are moving ever closer to their dream coming true. The SVR film team caught up with some of the Trust recently at Bridgnorth, and the video includes them moving the loco’s pony trucks into position for fitting to the locomotive. 

 

The hope is that 82045 will steam for the first time in late 2023, and the film showcases the Trust’s dedication and determination, as well reflecting on the fact that this will be the only Standard Class 3 tank in existence. All-in-all, it’s an exciting project, and one which should prove hugely worthwhile for the Railway. 

Grab a cuppa, sit back and enjoy the video on the SVR YouTube channel. If you can give us a like and subscribe to the channel too, we’d be grateful. 

Resurrecting a lost locomotive class at Bridgnorth

6045’s day in the spotlight

On Sunday 17th October, the Great Western (SVR) Association officially commemorated the return to service of GWR Collett bow-ended corridor composite 6045 (see October’s Express Points) with a special train for supporters and volunteers, as the Association’s Gareth Price reports: 

Hauled by 1501, the train consisted of 6045 with fellow bow-ender Saloon 9103, Art Deco brake third 650, and Toplight corridor third 3930, all of which are owned and restored by the Association.

 

The train departed Kidderminster at 10.45 and ran through to Bridgnorth where there was a toast for all the guests and a short presentation, conducted by Association chairman Mick Haynes and SVR managing director Helen Smith.

 

As well as thanking volunteers for their hard work in restoring the carriage, Mick also thanked the supporters who had so generously donated to the fundraising appeal for the project. A special thanks was made to Robert Smallman who purchased the vehicle in 1972 for £250; nearly 40 years ago this represented a tidy sum! 

The train then moved to Highley for lunch, before returning to Kidderminster later in the afternoon. The trip was thoroughly enjoyable, with many compliments received for the star attraction.

6045 was built at Swindon in 1928 and, along with other bow-ended designs, was formed into sets for the express services of the day. As newer, flat-ended designs proliferated throughout the 1930s, the bow-enders were gradually demoted to secondary services. Many lasted in service until the late 1950s or early 1960s. Seven composites survived into departmental use, with 6045 converted for use as a sleeping and mess van in 1961. It was saved for preservation from Bristol in 1972. It is the only bow-ended composite to survive, so has some historical importance. It had to wait patiently in the restoration queue for many years, with work starting in 2015. The work took five years and cost approximately £150,000. It will see use on the SVR in the historic Great Western set.

 

Click on the gallery for full screen images, descriptions and credits. 

6045’s day in the spotlight

Looking forward to 2022

content.jpg

In October’s Express Points we announced dates for the Spring Steam Gala and the Spring Diesel Festival. We can now announce further dates for enthusiast events: 

 

  • 2nd and 3rd April - start of public services for the 2022 season 

  • 9th and 10th April - daily running commences, continuing throughout the Easter holiday period. 

  • 21st to 24th April - Spring Steam Gala 

  • 7th and 8th May - Model Railway Weekend 

  • 19th to 22nd May - Spring Diesel Festival 

  • 15th to 18th September - Autumn Steam Gala

  • 24th and 25th September - Model Railway Weekend 

  • 29th September to 2nd October - Autumn Diesel Bash 

The full 2022 events calendar is being agreed with heads of department and we’ll let you have full details in a future edition of Express Points.

Photo: Class 17 D8568 Departing Bewdley Station on 3rd October during the Autumn Diesel Gala with a local train to Kidderminster. Credit Kenny Felstead

Looking forward to 2022

No rest for the infrastructure department! 

Planning is underway for winter as infrastructure manager Chris Bond tells Express Points, despite staff shortages (see separate article): 

Although we won’t be carrying out large projects this year, partly as we are still in recovery mode from the pandemic, there will nevertheless be some smaller in-house projects to address several longstanding problems. 

  

  • Replacement of point timbers identified as part of a Railway-wide survey. Some of these will require lifting of the metal components as there is insufficient room either side to slide in the replacements. 

  • We hope to build the mirror turnout at Foley Park (see May’s Express Points) to create a crossover; this is part of creating the first access into the area where we hope to develop a PW yard with loco unloading facilities in the future. 

  • Subject to SVR Holdings board approval, we intend to remove a deep area of ballast at Sterns caused by successive tamping over the years, and replace with a special light weight fill material. This should reduce the weight on the area by over 50%, which should help to slow down the movement we experience at the north end of the slip site.  

  • Drainage works are planned to the south of the foot crossing near milepost 144½ (‘Charlie Davies’ crossing’) near Country Park Halt. This will extend and improve previous work carried out in early 2019 to deal with rainwater that is percolating through the SVR formation. 

  • Other minor PW rectification works at various locations along the line. 

Although not an SVR project, the footbridge replacement at Kidderminster is still proceeding with Network Rail and the SVR making final preparations for the beginning of the contract. 

Bewdley North signal box fireplace November 2021. Chris Bond COPY.jpg
Kidderminster Footbridge OWW104 Autumn 2021.png

Our compound will be used by Story Contracting from 6th December for site set up, with actual work on the bridge commencing in earnest on 5th January 2022. The picture shows an augmented reality visualisation of what the bridge will look like. We’ll update you as the projects progresses. 

Finally, during October repairs were carried out to the open-fire cast-iron range in Bewdley North signal box. Our volunteer colleague Rob Hendrie instigated the repair via the infrastructure office, and I’m sure you will agree that it makes becoming a signalman a very attractive proposition! It’s important that we maintain these sort of heritage details so that we can preserve for future generations the ambience of what a steam railway was, in all its aspects. 

Bewdley North signal box fireplace November 2021. Rob Hendrie

Kidderminster Footbridge OWW104 Autumn 2021

No rest for the infrastructure department! 

Your Permanent Way needs you!

Midland Metro have donated rails to the SVR and this was delivered to Eardington on 28th O

Express Points readers will know that the Severn Valley Railway is 16 miles long and runs through some beautiful countryside. What is perhaps less well-known is just how much maintenance is required to keep the track safe and up to standard. Infrastructure manager Chris Bond has an appeal for help:

  

The SVR has carried out a great deal of recruitment activity for permanent way (PW) work which, unfortunately, has not yet been successful.

 

This leaves us facing considerable difficulties in recruiting paid staff. Work continues on the best way to resolve the staffing problems so that we can have the structure we need to maintain the SVR’s substantial track assets.

At the same time, we face reducing numbers of volunteers in the department. 

That’s partly a consequence of Covid-19, which has seen some staff not return to active duty, and partly natural wastage in a department with a decidedly ‘top end’ age profile. Our stalwarts do a magnificent job, but need assistance to ease the burden.

The combination of the two issues gives cause for concern. One of the most important areas where we are starting to see problems is rostering the weekly line patrols, a requirement of our Safety Management System (SMS). We are compliant with our SMS, but it’s essential that we have some fresh blood on the PW volunteer side. If we don’t, then in the foreseeable future we would have to try and engage paid staff (and you will appreciate the difficulties we face, as outlined above), or we will have to take people off other, important maintenance work.

This is an appeal to working members in other departments to offer a bit of their time for this essential safety-critical routine, so that we can continue to meet the requirements of our SMS and ensure that potential safety issues are spotted and rectified before they become more serious.

We can do this, with volunteer good will. The work itself is not onerous. You’d need a valid PTS (Personal Track Safety, which can be arranged if not already held); a simple self-certification medical assessment (unless a valid one is already held); and sufficient physical fitness to walk several miles at a time. All personal protective equipment (PPE), tools and equipment will be provided.

We are investigating a route for external training in this discipline so that a recognised competency can be obtained by those who patrol our tracks, and this would be offered to any new recruits as and when it has been organised.

If you haven’t considered the PW before, now is an excellent time to expand your horizons and help keep the SVR’s track assets in good condition. Applications from all departments welcomed!

Interested? Please email either keith.brown@svrlive for Bewdley or brent.cleeton@svrlive.com at Bridgnorth. Go on - you know you want to…!

Photo: Midland Metro have donated rails to the SVR and this was delivered to Eardington on 28th October 2021. John Oates.

Your Permanent Way needs you!

Questions and answers – the Bridgnorth roof and crane project

Images roof and sides.jpg

The SVR’s final Q&A panel of the year took place last month and is now available online on the TODAY channel on Teams. For those lacking the time to watch the full video, this article and the one that follows it outline the key points covered.  

 

First on the agenda was the roof and crane project, with much of the discussion centred on the detailed planning and preparation involved. Martin White, head of engineering, explained how the site would need to be evacuated ahead of time, including relocating the Western Locomotive Association’s (WLA) workshops and storage facilities.

[A subsequent development is that WLA items and container will move to Kidderminster, and they will retain their workshop facilities and other storage/work containers at Bridgnorth for now at least - Ed.]

The expectation is to evacuate the site by the end of the year, with a detailed plan currently being drawn up to cover the removal and storage of everything affected. 

Martin also answered questions about the timing of the works, currently scheduled for Spring 2022, explaining that the 16-week project needed the best possible weather, and to avoid the event-packed winter season and the vital winter maintenance period. Martin further outlined how the work is scheduled to fall between the Spring and Autumn Galas, so as not to cause disruption to these important events.

Discussing the insulation, project manager Antony Bartlam emphasised the need to insulate the whole building to prevent history from repeating itself with the new shed roof. He noted the intention to install darker cladding so as not to show the dirt, and low maintenance translucent panels that could be safely cleaned using a cherry picker when required.

 

Martin fielded several questions about the impact of the project on productivity and volunteers, where he was emphatic about the value of volunteers and the importance of maintaining output: “After Covid-19, we never again want a time when volunteers aren’t welcome, and clearing the shed will need lots of volunteer labour.” Martin explained that the machine shop and boiler shop would continue to operate as normal whilst temporary work benches and covered facilities would be provided for the regular work required to maintain the fleet.

 

Antony observed that carrying out the roof and the crane elements of the project at the same time would minimise disruption with parts of the shed accessible again once the cladding is installed. Antony also echoed Martin, stressing the importance of volunteers on this project, expecting that rather than restricting volunteer labour, the project would call for an increase in volunteer activities.

 

Addressing concerns about inflated costs, SVR(H) director and Bridgnorth masterplan lead Graeme Bunker-James acknowledged the increased costs of materials, with the prices for steels and other components rising, but noted having this information ahead of contracts being placed was a positive.

 

Responding to fears that the roof and crane project could over run, managing director Helen Smith was firm that operations would not be affected: “I’m sure it will be challenging but we can’t afford to lose any operational work. The amount of planning and effort that has gone into this project, our project leaders have a really good handle on it and will work really closely with the contractors. There’s nothing unknown in the project, we know what’s on the land and it should go as planned, unless we get a plague of locusts…!”

Q & A Bridgnorth roof and crane project

More questions and answers – Bridgnorth station project 

The first question was about the delayed start date for this project. Project manager Neil Dancer explained this was because of the scarcity of materials, which had pushed the start date of work back from 2022 to 2023, and that the work was planned to take 16 weeks. 

Answering a question about phasing, Neil noted that replacement of the lean-to building was first on the agenda. Next on the list is the construction of the snug, with the waiting room left until last. Neil said: “The waiting room will be a good storage space while we effect the other works. This has been left to last as it’s deemed of the least importance, should the project not be fully completed in the allotted 16 weeks.” 

 

Neil dealt with a question about the possible expansion of the lean-to by adding a second storey during the rebuild, and explained that, given its historical significance, the building would have to be rebuilt in original form.

DSC_1218 (Copy).JPG

The ambience of the Railwayman’s Arms was raised, and managing director Helen Smith provided assurance that this was a key consideration, explaining that an advisory group was being established to consult on ideas for décor, and to ensure the feel of the pub didn’t change. Neil expressed the caveat that new fixtures and fittings for the snug in keeping with the period would not be cheap, and this needed to be taken into account. 

 

Replying to a question about accommodation for a store to serve the on-train services, Helen acknowledged there was an existing store, and that there is a need to review the situation, inviting the team to contact her for discussion on this.  

 

SVR(H) director and Bridgnorth masterplan lead Graeme Bunker-James answered a request for an update on the Bridgnorth turntable, stating that before the turntable could be installed, the yard would first need to be re-laid; allowing a platform 2 extension and enabling track to reach the turntable location. Replying to further questions Graeme also noted that, whilst it was not wholly ruled out, at present there were no plans for a further appeal for the turntable, and he praised the volunteer work being carried out to refurbish the components.  

 

The next ‘hot button’ issue was car parking at Bridgnorth and the proposals to install automatic number plate recognition. Helen Smith fielded this, stating that planning for this was still in the discussion stage, with a number of factors to be considered but that the geography of the site meant ANPR was the only viable option: “It’s becoming quite common now. We’ve looked at every other option and it’s not possible because of the geography of the site. I’m expecting some issues to start with, but people will soon get used to it.” 

 

How to prevent the Bridgnorth project from going over budget? Neil Dancer was firm that the scheme will be tailored to the budget, placing functionality first: “If we can achieve a good build with the right ambience, we might have flexibility to include the elaborate period fittings.”  

More Q & A's - Bridgnorth station project 

George Heiron – railway artist and photographer

The SVR’s YouTube channel recently launched the first in a new series of videos, each of which will delve into the trove at The Engine House, Highley. The series aims to uncover the treasures here, some of which are very obvious, and some of which are more tucked away in the SVR’s archive.  

 

This time round, we focus on the work of George Heiron, a renowned railway photographer and artist. Our film crew visited in the company of George's son, Richard Heiron, who talked about his father's love of railways, his work, and the two Stanier 8F pictures on display close by locomotive no. 48773 of that class. 

 

We hope you enjoy the film, and that it whets your appetite for future videos in the series. 

George Heiron – railway artist and photographer

Two decades of the Kidderminster Carriage Shed!

On the 29th November, Kidderminster Carriage Shed will celebrate its 20th birthday. Whilst the carriage shed might not attract visitors to the Railway in the same way that the SVR’s locomotives and beautifully-kept stations do, it is integral to the running of the SVR and no less worthy of celebration!

Plans for a carriage shed were first mooted in 1979, and these plans were deferred and changed as the shape of the Railway changed and grew.

 

In the late 1990s, applications were made to the Heritage Lottery Fund, seeking £6.5million for a traditional-style locomotive shed. After much back-and-forth, approval to fund a modern design was granted, and the Railway was awarded £1,757,000 towards construction of the carriage shed. At the time, this was the largest grant the HLF had made to a heritage railway!

As the then-SVRA worked to raise the remaining funds, carriages and wagons that had previously occupied sidings on the site of the new carriage shed, needed new homes, as longstanding SVR volunteer Hugh McQuade recalls:

“I surveyed the sidings and stations all along the Railway and worked out that all of the eight-coach trains could be parked up in platforms at Kidderminster, Bewdley and Bridgnorth. The attractive goods wagons were sent to Highley, Arley and Bewdley Down Yard where they could be viewed by passengers. The engineering wagons found a home at Eardington sidings and the Stourport branch spur.”

The Tenbury branch remnant at Bewdley North was also extended to the public foot-crossing, to provide a home for the GWR rake, and the diesel locomotives were corralled into the sidings at Kidderminster, now the site of the Traction Maintenance Depot.

20191128_122200.jpg
Carriage Shed Plaque. Robin Childs.jpg

Construction of the building began in September 1999, and was completed on 19th April 2000. On November 29th 2001, the shed was formally opened by railway enthusiast, SVR patron and cousin to the Queen, HRH The Duke of Gloucester. The Duke rode on a special train to Bewdley, taking the controls of A4 60009 Union of South Africa for a brief stint. The opening is commemorated on a plaque on the side of the shed.

 

The benefits of the carriage shed are indisputable; previously a new paint job would last seven years, requiring a full strip back and build-up of primer layer, three surfacers, two undercoats, two gloss coats and two layers of varnish. The upholstery would also have been gradually bleached by the UV light outdoors. By contrast, 10 years after moving into the shed, it was decided to repaint 25346. Whereas previously, staff would have found ruined paintwork, the coach exterior was still smooth to the touch; only half the work previously carried out was required. Per coach, this saves £450 in paint alone, not to mention the staff hours, which can now be spent elsewhere. Hugh also estimates storing the carriages indoors extends the life of the upholstery by up to five years!

So, happy 20th Birthday to Kidderminster Carriage Shed and here’s to the next two decades!

Photo: top, from SVR photo library

Below: Credit Robin Childs

National Lottery Heritage Fund logo.jpg
Two decades of the Kidderminster Carriage Shed!
Staddle Up!

Staddle Up!

Staddle stones 2. Terry Plumb.jpg

A new feature recently arrived at Arley station’s beautiful gardens, that’s both attractive and has a fascinating history. 

 

The story starts back in the summer when Terry Plumb and Malcolm Broadhurst were approached at Arley Station by a lady offering them mushrooms; nothing nefarious here, these ‘mushrooms’ were made of sandstone, and were in fact staddle stones.

 

Staddle stones were originally used across the UK in the 18th and 19th centuries as a means of raising grain stores and larders off the ground, to increase air circulation and protect them from flooding. The mushroom shape also prevents vermin from climbing the stones and getting inside the store. The curious name ‘staddle’ derives from the old English word stathol, which means base or support. Carved by local stonemasons, each stone would be unique, and they’re quite a sought-after garden ornament.

The two staddle stones offered to the SVR are likely to be over 100 years old. They were collected by Terry and John Pitman, much to the detriment of John’s van’s suspension! To make them sturdy and safe, the SVR's master stonemason Philip Chatfield happily volunteered to replace the locating tubes securing the tops to the pedestals, which over the years had corroded away. Once set in position, the staddles were then ready to be relocated.

 

The Thursday gang worked away at locating them in the border identified as the most suitable and visually pleasing place and the staddle stones are now happily situated, with a modest plaque to recognise their kind donation, made by Alison and Phil Walton. Terry Plumb said:

 

“We would like to thank everyone involved in getting these located within the station gardens. Next time you take a walk along the down platform, have a look for them. You can’t miss them in the border beneath the Arley running-in board, and they make a wonderful addition to the beautiful gardens at Arley.”

Staddle stones at Arley, Terry Plumb

Testing, testing 

In July and August’s Express Points operations manager Matt Robinson gave details of the Bayer weedkilling test train. It has returned for further testing, as Matt told Express Points.


The SVR are again providing testing facilities for Bayer CropScience Uk who are producing a fleet of weedkilling trains for the UK Network. Following an intensive programme of testing in June / July 2021 a reworked train 1 has just returned to the SVR for further tests to be carried out soon. It is hoped trains 2 & 3 will follow in due course for their acceptance tests.


On Monday 8th November the train arrived from Loram, Derby. The train was operated by Loram Rail Operations and worked by 20007 and 20205.

31466 waiting to leave Bewdley for Waterworks (just north of Hampton Loade) on 9th Novembe

The following day the SVR provided test facilities for one day of camera calibration works. Unusually this was done at Waterworks rather than the normal test location of Bewdley tunnel, and the order of the day was ‘static’ testing. The train will now be stored on the SVR, the main testing not due to start for at least several weeks.


Meanwhile, the last remaining HST power car 43277 is being moved up to Highley today (11th November) for further stabling, making space for Santa operations set up at Arley.

Photo: 31466 waiting to leave Bewdley for Waterworks (just north of Hampton Loade) on 9th November 2021. Matt Robinson

Testing, testing

Skills surplus and requirements

Surplus_1.jpg

The items advertised as surplus in October’s Express Points news item were well received, and Bewdley station were able to pass on several surplus bikes to good homes. This month, there’s a surplus and a couple of ‘requirements’. 

  

Bewdley station is looking for some lockers to use in conjunction with their accommodation. Has anyone along the line has any that are surplus to requirements? Please contact Dai Phillips at Bewdley.   

  

Bridgnorth station is on the lookout for any surplus GWR spearhead panels; they require 15 panels, hopefully in reasonable condition, as part of the enabling and public realm works for the Bridgnorth station conservation and renovation project. Please contact Chris Thomas at Bridgnorth. New ones, if ordered, would be very expensive! 

 

Russell Maiden has kindly donated an electric stove style heater for use (with appropriate checks) on the railway. It is too large for the signalboxes, but is there any department that would have a use for it? Contact richard.cooper@svrlive.com

Skills surplus and requirements

V1 11th November 2021

Need to contact us?

Branch Lines Logo3.png

A dedicated newsletter for SVR supporters - Branch Lines

A monthly newsletter dedicated to SVR Supporters has been created, this allows Express Points to be directed to our working members. ​CLICK HERE for the latest edition of Branch Lines.

If you're a supporter of the SVR, but not a Working Member then please email BranchLines@svrlive.com to be added to the distribution list

Thanks for reading!

If you receive our monthly newsletter by email and wish to unsubscribe from our newsletter please email ExpressPoints@svrlive.com

Any opinions or views expressed in this newsletter are entirely the opinions of the contributors, and do not necessarily reflect the opinions of the Directors of Severn Valley Railway (Holdings) PLC. which owns the Severn Valley Railway, Severn Valley Railway Company Limited, the members of which are responsible for its operation, or the Severn Valley Railway Charitable Trust.